The city held a pre-construction meeting, February 23 on the Broad Street infrastructure upgrade.  construction is attentively scheduled for March 19, 2018.  Sanitary and storm sewer replacement will begin at this time from the intersection of Broad Street and North Second Street down to the railroad tracks on Broad Street.  Utility relocation, newly constructed ADA compliant sidewalks and LED street lighting will follow.  Estimated time of completion is 180 days from starting date.  After nearly 3 years of planning, collecting funds (1.55 million dollars in grants) and coordination with all utility companies, the time for Central City’s transformation and infrastructure upgrading is finally here.  There is more good news coming for the city as we continue to improve our infrastructure and appearance moving forward.